REPORTS-Consultancy/Services

UGD-Consultancy/Services

Sector: UGD
Project Name ULB Value of Works (in Rs. Cr) Name of Consultancy /Agency Starting Date Completion Date Status Grade
KIUWMIP Davnagere Rs 1.08 Crore M/s SCODWES 05-05-2017 04-05-2019 Identification of beneficiaries for toilet construction, formation of community groups for promotion of toilet construction and awareness creation on sanitation Satisfactory
KIUWMIP Harihara, Byadgi and Ranebennur Rs 1.08 Crore M/s NEEDS 05-05-2017 04-05-2019 Identification of beneficiaries for toilet construction, formation of community groups for promotion of toilet construction and awareness creation on sanitation Satisfactory
KIUWMIP Harihara, Byadgi and Ranebennur Rs 1.08 Crore M/s NEEDS 05-05-2017 04-05-2019 Identification of beneficiaries for toilet construction, formation of community groups for promotion of toilet construction and awareness creation on sanitation Satisfactory
KMRP Doddaballapur Rs 28.15 Crore M/s WAPCOS, Ltd 14.09.09 31.03.16 Completed Un-satisfactory
KMRP Chikkaballapura Rs 27.11 Crore M/s WAPCOS, Ltd 09.03.10 31.07.14 Completed Un-satisfactory
KMRP Tiptur Rs 22.93 Crore M/s WAPCOS, Ltd 28.05.10 21.11.11 Completed Satisfactory
KMRP Tiptur Rs 18.3 Crore M/s WAPCOS,Ltd 15.10.15 31.05.17 Completed Satisfactory
KMRP Hassan Rs 4.41 Crore M/s WAPCOS, Ltd 17.06.08 30.04.11 Completed Satisfactory
KMRP Chintamani Rs 1.8 Crore M/s WAPCOS, Ltd 22.03.11 10.07.13 Completed Satisfactory
KMRP Bhadravati Rs 23.3 Crore M/s WAPCOS,Ltd 04.10.12 31.12.17 Work under Progress Un-satisfactory
KMRP Humnabad Rs 28.57 Crore M/s Shah Technical Consultants Pvt. Ltd 29.01.13 31.12.17 Work under Progress Un-satisfactory
KMRP Harihara Rs 24.4 Crore M/s Shah Technical Consultants Pvt. Ltd, 09.11.16 08.04.18 Work under Progress Un-satisfactory
Sector: UGD Project Name ULB Value of Works (in Rs. Cr) Name of Contractor/Agency Starting Date Completion Date Status Grade KIUWMIP Davanagere 110 M/s Simplex Infrastructures Ltd 09-01-2015 08-01-2018 70%(115 km) B KIUWMIP Davanagere 39.9 M/s HNB Engineers Pvt. Ltd 28-09-2015 27-09-2019 91% A KIUWMIP Harihara 62.75 M/s Shriram EPC Ltd 09-01-2015 31-01-2018 78% (72.58 km) B KIUWMIP Byadgi 64.49 M/s. Shriram EPC Pvt. Ltd and Eurotek Environmental Pvt. Ltd-JV 16-04-2016 15-04-2019 31% (34.59 km) A KMRP Doddaballapur Rs 28.15 Crore M/s RAUS Constructions Pvt Ltd 14.09.09 31.03.16 Completed Un-satisfactory KMRP Chikkaballapura Rs 27.11 Crore M/s Ramky Infrastructure Ltd 09.03.10 31.07.14 Completed Un-satisfactory KMRP Tiptur Rs 22.93 Crore M/s KBR Infratech Ltd., Bangalore 28.05.10 21.11.11 Completed Satisfactory KMRP Tiptur Rs 18.3 Crore M/s Khilari Infrastructrure, Mumbai 15.10.15 31.5.17 Completed Satisfactory KMRP Hassan Rs 4.41 Crore M/s H.V. Krishna 17.06.08 30.04.11 Completed Satisfactory KMRP Chintamani Rs 1.8 Crore M/s Sree Subha Sales 22.03.11 10.07.13 Completed Satisfactory KMRP Bhadravati Rs 23.3 Crore M/s Abhiram Infrastructure Pvt Ltd, Hyderabad 04.10.12 31.12.17 Work under Progress KMRP Humnabad Rs 28.57 Crore M/s. GORUR INFRA PROJECTS PVT LTD,MUMBAI 29.01.13 31.12.17 Work under Progress KMRP Harihara Rs 24.4 Crore M/s. Eiffil Constructions Pvt Ltd,Ahmedabad 9.11.16 8.4.18 Work under Progress