Kalaburgi Division
                 
Town Component Package Contractor Date of Contract award Date of Completion Extended date of Completion Original Contract Amount (Cr.) Revised Contract Amount
(Cr)
Bidar DIC 02DIC02 Mr. Rajashekhar K. Patil 09.11.2010 08.01.2018 Completed 0.5 0.47
WS 02BDR01 M/s. Megha Engineering 30.03.2011 29.10.2012 31.10.2015 28.03 28.03
WS 02BDR01A M/s. Megha Engineering 30.03.2011 29.10.2012 31.01.2016 27.58 27.58
UGD 02BDR02 M/s. Ayyappa JV with Megha Engineering 22.07.2011 21.07.2013 21.07.2016 39.8 43.55
Tourism 03BDR03 Mr. Gurunath Kollur 17.07.2013 16.12.2014 16.03.2016 2.41 3.7
Khandak (Cleaning) 03BDR02A Mr. Gurunath Kollur 14.02.2014 13.08.2014 Completed 4.23 4.09
UGD 03BDR02 Mr. Gurunath Kollur 27.05.2014 26.11.2015 26.11.2016 19.01 19.01
24 X 7 WS 04BDR01 M/s. Vishwaraj Infrastructures 30.01.2015 29.06.2017 18 months 42.92 42.92