Town Component Package Contractor Date of contract award Date of completion Extended date of Completion Original Contract Amount (Cr) Revised Contract Amount
(Cr)
Davanagere WS 02DVG01 M/s. Salcon Engineering 22.08.2011 21.02.2013 31.12.2014 24.28 27.43
UGD 03DVG02 M/s. Abhiram Infra Projects 17.02.2014 16.08.2015 31.05.2016 33.25 35.76
STP 03DVG02A M/s. HNB Engineers 19.02.2014 24.12.2015 23.06.2016 29.49 30.25