Town Component Package Contractor Date of contract award Scheduled date of completion Extended date of completion Contract amount in Cr Revised Contract amount in Cr
Gangavathi Drainage 02GTI01 M/s. Ramky Infrastructure 03.03.2010 31.05.2011 30.09.2013 9.449999999999999 4.9
Slum improvement 02SCB04 Sri Amarkhed, Raichur 31.03.2010 30.06.2011 6.69 2.95
Slum improvement 02GTI06 Siddaramanagowda 23.04.2015 24.07.2016 3.92 3.92