     Town Component Package Contractor Date of contract award Date of completion Extended date of Completion Original Contract Amount (Cr.) Revised Contract Amount
(Cr)
Nippani WS 02NPN01 (Terminated) M/s Tapi Prestressed 10.05.2010 10.11.2011 30.06.2015 13.11 14.8
WS 02NPN01 Tender under evaluation
24 X 7 WS 04NPN01 M/s Jain Irrigation 28.08.2014 27.05.2016 21.11.2016 19.66 19.66
Slum improvement 02NPN06 V A Dharav 28.01.2015 27.10.2015 27.03.2016 0.26 0.276