Town Component Package Contractor Date of contract award Scheduled date of completion Extended date of completion Contract amount in Cr Revised Contract amount in Cr
Raichur WS 01RCR01 M/s. Sai Sudhir Infrastructure 01.04.2010 30.09.2011 31.12.2013 14.2 14.44
24 X 7 WS 04RCR01 M/s. SPML 28.02.2015 27.08.2017 - 79.93000000000001 79.93000000000001
UGD 01RCR02 (Terminated) M/s Coramandal 04.10.2010 03.04.2012 39.81 6.56
UGD 02RCR02 M/s. Swastik 28.12.2015 27.12.2017 - 41.2 41.2
UGD 04RCR02 M/s. Swastik 28.12.2015 27.12.2017 - 42.47 42.47
Lake Improvement 04RCR04 M/s. M. Sudhakar Infratech 20.04.2016 19.04.2017  - 2.76 2.76