Town Component Package Contractor Date of contract award Date of completion Extended date of Completion Original Contract Amount (Cr) Revised Contract Amount
(Cr)
Ranebennur UGD 02RNR02 (Terminated) M/s. Ramky Infrastructure 23.06.2010 22.12.2011 20.03.2015 35.53 21.87
UGD 02RNR02A M/s. Ayyappa Infra Projects 25.03.2015 25.03.2017 - 64.94 64.94
UGD 02RNR02B Sri. Guru Raghavendra 11.08.2016 10.05.2017 - 8.40 8.40
Slum improvement 02RNR06 S.G. Srinivasa Reddy 20.03.2015 19.03.2016 - 0.95 0.75